Sit is upgrading the shared apartments at Moholt alle

Sit
Sit

Sit is upgrading the shared apartments at Moholt alle

The time has come to show some extra love for the shared apartments and the surrounding outdoor areas at Moholt alle - and we're talking a massive upgrade, both inside and outside.

Status today

Moholt alle 1, 2, 3, 4, 5, 6, 7, 8, 10, 12, 14 and 16 are finished. Work has begun in Moholt alle 18, 20, 22, 24, 26 and 28. See pictures of the new shared apartments further down the page!

Work on upgrading the entire area will continue until December of 2023, and there will be work on the outdoor areas throughout the period. Some periodic noise is to be expected.

The outdoor areas

Illustrasjon av utvendig oppgradering i Moholt alle

We're changing the area between Moholt alle 7 and 11 into a large, multi-purpose space for our tenants. We'll put up roofed benches and tables, a climbing wall, an outdoor bicycle wash and repair shop, and a community garden (allotment).

We're also building a geothermal heating plant, that can supply thermal heating of water and ventilation air for everyone living in the shared apartments in Moholt alle. The facility extracts heat from 300 meters below the ground, through 14 wells located on the plot behind the heating plant. The plant also recycles ventilation air and wastewater from the buildings. Pretty awesome stuff, in other words!

Illustrasjon av utvendig oppgradering i Moholt alle

We're removing the roundabouts and making the entire area greener - there will only be access strictly necessary driving to and from the buildings. We will be putting up several outdoor grills and lockable bicycle sheds in the area as well.

The shared apartments

Renovated shared apartment in Moholt alle

The shared apartments will be completely renovated and upgraded. The common area will have a new, cozy sitting area.

Private room in renovated shared apartment in Moholt alle

Private room in renovated shared apartment in Moholt alle

The private rooms will have bespoke furnishing All you need to bring from now on, is your own mattress!

New studio apartments in the basements

We're also making brand new studio apartments in the basements, in the areas where there are two-man apartments and bicycle parking today.

Scheduled progress

  • December 2020 – Start work on outdoor areas around Moholt alle 1,3,5 and 7
  • Summer 2021 – Outdoor areas around Moholt alle 1,3, 5 and 7 are finished, and work start around the remaining buildings with shared apartments. Start work inside Moholt alle 1,3, 5 and 7.
  • December 2023 – Upgrading of the entire area is finished.